SAMPLE DATA — FICTIONAL PROJECT · ILLUSTRATIVE BID-LEVELING FORMAT (NO REAL CLIENT DATA)

3-Vendor Supplier Quote Leveling & Award Dashboard

Fictional Package: 500 kWp Commercial Rooftop Solar PV & AC Switchgear Upgrade · Apples-to-apples normalization of freight, omitted scope, lead times, and commercial exclusions.

Sample Data — Fictional Project
Recommended Award (Normalized)
Vendor B — $446,200
Lowest compliant landed cost · 6-week lead time
Hidden Scope Caught on "Cheapest" Bid
+$51,300
Vendor A omitted AC switchgear, craneage & port freight
True Net Savings vs. Vendor A
$23,600
5.0% margin protected before PO issue
Spread Across 3 Bids (Normalized)
$36,900
$446,200 (Vendor B) to $483,100 (Vendor C)
Line-by-Line Commercial Comparison Matrix (Showing Normalized Landed Cost — omitted items priced at market allowance)
Item Category Qty / Unit Vendor A (Apex) Vendor B (Meridian) Vendor C (Summit) Commercial Flag
Vendor Commercial Risk & Exclusion Summary

Vendor A — Apex Solar Supply 3 Omissions

Headline: $418,500 → Normalized: $469,800 · Lead: 9 wks
  • Omitted: 800A main AC tie-in switchgear ($28,500 allowance added).
  • Omitted: Port-to-site freight & craneage ($14,800 allowance added).
  • Omitted: Utility witness testing ($8,000 allowance added).
  • Payment terms: 50% upfront deposit (higher cashflow risk).

Vendor C — Summit Commercial High Rate

Headline: $477,600 → Normalized: $483,100 · Lead: 5 wks
  • Fastest delivery (5 wks) but +8.3% above Vendor B on equipment.
  • Exclusion: Engineering RPEQ/PE roof wind-load cert ($5,500 added).
  • Backup option only if schedule is critical by 1 week.